| 26-1251-AN | Advance submission-GMP/248-Towns of Woodstock, Hartford, and Hartland | Closed | Case Age: 55 | ||
| Regulatory / Advance Notice: Closed | Date filed: 06/24/26 | ||||
| Green Mountain Power Corporation [Petitioner] | |||||
| Green Mountain Power Corporation [Utility Company] | Electric | ||||
| 1 Issue(s):§ 248 | 3 Location(s):Woodstock | ||||
Summary-Portal
|
Caption: 45-day advance submission of Green Mountain Power, pursuant to 30 V.S.A.§ 248, for approval to relocate and rebuild GMP's Taftsville Substation in the Towns of Woodstock, Hartford, and Hartland, VT
|
| Date Filed | Project Type | Project City | Project Address | Status | Ref. No. | |
|---|---|---|---|---|---|---|
|
|
06/24/2026
|
§ 248
|
Woodstock
Hartland Hartford |
|
Closed
|
26-1696-PET
(Open)
|