09/11/2026
|
If stipulation or settlement: Proposed findings deadline if evidentiary hearing is requested
|
26-0651-PET
|
|
|
|
08/27/2026
|
If stipulation or settlement: Tentative evidentiary hearing if requested, or deadline for proposed findings if no hearing is requested
|
26-0651-PET
|
|
|
|
08/14/2026
|
If no stipulation or settlement: Deadline for submitting proposed schedules for litigation of any contested issues
|
26-0651-PET
|
|
|
|
08/12/2026
|
If stipulation or settlement: Deadline for parties to file stipulations and any requests for a hearing
|
26-0651-PET
|
|
|
|
07/15/2026
|
Deadline for GMP to respond to round two discovery
|
26-0651-PET
|
|
|
|
07/01/2026
|
Deadline for round two discovery on GMP
|
26-0651-PET
|
|
|
|
06/24/2026
|
Deadline for GMP to respond to round one discovery by intervenors, if any
|
26-0651-PET
|
|
|
|
06/10/2026
|
Deadline for round one discovery on GMP by intervenors, if any
|
26-0651-PET
|
|
|
|
06/03/2026
|
Deadline for GMP responses to round one discovery by parties
|
26-0651-PET
|
|
|
|
05/28/2026
|
Deadline for responses to motions to intervene
|
26-0651-PET
|
|
|
|
05/20/2026
|
Deadline for round one discovery on GMP by parties
|
26-0651-PET
|
|
|
|
05/15/2026
|
Deadline for motions to intervene and deadline for requesting public hearing and/or site visit
|
26-0651-PET
|
|