Petition |
|
|
04/8/26 Second Step |
|
|
04/8/26 Direct Prefiled Testimony |
|
|
|
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-1 |
Existing Operating Diagram |
Other |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-2 |
Rebuilt Substation Operating Diagram |
Other |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-3 |
Site Plan |
Site Plan |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-4 |
Plan View |
Site Plan |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-5 |
North Elevation AA |
Elevation Drawings |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-6 |
East Elevation BB |
Elevation Drawings |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-7 |
West Elevation CC |
Elevation Drawings |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-8 |
South Elevation DD |
Elevation Drawings |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-9 |
Proposed Oil Containment |
Other |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP JRF-10 |
Temporary Substation Operating Diagram |
Other |
Green Mountain Power Corporation [PET]
|
Fiske, John [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Second Step |
|
|
04/8/26 Direct Prefiled Testimony |
|
|
|
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-1 |
Resume |
Resume |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-2 |
Natural Resources Assessment |
Other |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-3 |
Archaeological Review |
Other |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-4 |
Sound Study |
Other |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Second Step |
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-5 Part I of II |
Aesthetics Analysis with Appendices A-D |
Other |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Second Step |
|
|
04/8/26 Exhibit |
Exhibit GMP-AC-5 Part II of II |
Aesthetics Analysis with Appendix E |
Other |
Green Mountain Power Corporation [PET]
|
Crary, Adam [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Second Step |
|
|
04/8/26 Direct Prefiled Testimony |
|
|
|
Green Mountain Power Corporation [PET]
|
Hassan, Kamran A [WIT]
|
Filed
|
Public |
|
|
|
04/8/26 Exhibit |
Exhibit GMP-KAH-1 |
Project Cost Estimate |
Other |
Green Mountain Power Corporation [PET]
|
Hassan, Kamran A [WIT]
|
Filed
|
Public |
|