Vermont Public Utility Commission

26-0651-PET GMP/request for CPG for rebuild of Georgia substation-Georgia Open Case Age: 60
Regulatory / Petition: Open Date filed: 04/8/26
Hearing Officer   Date Administratively Complete: 04/21/26
Green Mountain Power Corporation [Petitioner]  
Green Mountain Power Corporation [Utility Company]   Electric
1 Issue(s):§ 248   1 Location(s):Georgia  

Summary-Portal

 

Caption: Petition of Green Mountain Power for a certificate of public good, pursuant to 30 V.S.A. § 248, authorizing the rebuild of the Georgia substation in Georgia, Vermont

Date
Filed
Town
   
Project Size
(in acres)
Generation
Type
Generation
Size
Construction
Related
Std. Offer
Project
Related
CPG No.
Adv. Notice
Ref. No.
Other Rel.
Case No.
04/08/2026
Georgia
Yes
No
26-0238-AN (Closed)
 
Name(s) Address Telephone Email
  Green Mountain Power Corporation [PET] Mailing
163 Acorn Lane
Colchester, VT 05446
Work:
(802) 655-8768
    Debra L. Bouffard, Esq., Sheehey Furlong & Behm [REP] Mailing
30 Main Street, 6th Floor, P.O. Box 66
Burlington, VT 05402-0066
Work:
(802) 864-9891
Primary Email:
dbouffard@sheeheyvt.com