Vermont Public Utility Commission

26-0540-PET Savage Solar Energy, LLC/2.75 MW-Chester Open Case Age: 168
Regulatory / Petition: Open Date filed: 03/23/26
Hearing Officer   Date Administratively Complete: 04/1/26
Savage Solar Energy LLC [Petitioner]  
Green Mountain Power Corporation [Utility Company]   Electric
1 Issue(s):§ 248   1 Location(s):Chester  

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    May 5, 2026 11:00 AM Scheduling Conference via videoconference Noticed Hearing Officer Held 05/05/2026
Due Date Name Related to Filed by
08/07/2026
Deadline for Petitioner to file Proposed Findings of Fact, Order & CPG (if case is not contested)
26-0540-PET
07/31/2026
Deadline for parties to file proposed schedule for remainder of litigation (if case is contested)
26-0540-PET
07/24/2026
Deadline for Comments/Stipulations and associated testimony/exhibits (if any settlements are reached)
26-0540-PET
07/13/2026
Deadline for Petitioner’s responses to Second Round of Discovery
26-0540-PET
07/01/2026
Due date for Petitioner to provide the information requested in 6/17/26 order.
26-0540-PET
06/26/2026
Deadline for second round of Discovery to be served on Petitioner (if necessary)
26-0540-PET
06/05/2026
Deadline for Petitioner’s responses to First Round of Discovery
26-0540-PET
05/22/2026
Reply to Response to Motion Due Date (if any response filed)
04/29/26 Motion to Intervene
Division for Historic Preservation [P]
05/18/2026
Deadline for first round of Discovery to be served on Petitioner
26-0540-PET
05/15/2026
Response to Motion Due Date
04/29/26 Motion to Intervene
Division for Historic Preservation [P]
05/15/2026
Deadline for responses to motions to intervene
26-0540-PET
05/12/2026
Deadline for motions to intervene and requests for public hearing and site visit
26-0540-PET
 
Print this Page