26-0238-AN Advance submission-GMP/248-Georgia Substation-Georgia Closed Case Age: 63
Regulatory / Advance Notice: Closed Date filed: 02/4/26
 
Green Mountain Power Corporation [Petitioner]  
Green Mountain Power Corporation [Utility Company]   Electric
1 Issue(s):§ 248   1 Location(s):Georgia  

Summary-Portal

 

Caption: 45-day advance submission of Green Mountain Power, pursuant to 30 V.S.A.§ 248, for approval to upgrade GMP's substation at the Georgia substation in Georgia, VT

Date Filed Project Type Project City Project Address Status Ref. No.
02/04/2026
§ 248
Georgia

Closed
26-0651-PET (Open)
Name(s) Address Telephone Email
  Green Mountain Power Corporation [PET] Mailing
163 Acorn Lane
Colchester, VT 05446
Work:
(802) 655-8768
    Debra L. Bouffard, Esq., Sheehey Furlong & Behm [REP] Mailing
30 Main Street, 6th Floor, P.O. Box 66
Burlington, VT 05402-0066
Work:
(802) 864-9891
Primary Email:
dbouffard@sheeheyvt.com