Vermont Public Utility Commission

25-2412-PET GRH Growth, LLC/3.5 MW-Vernon Open Case Age: 335
Regulatory / Petition: Open Date filed: 10/7/25
Hearing Officer   Date Administratively Complete: 10/14/25
GRH Growth LLC [Petitioner]  
National Grid [Utility Company]   Electric
1 Issue(s):§ 248   1 Location(s):Vernon  

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    May 26, 2026 9:30 AM Evidentiary Hearing via videoconference Noticed Hearing Officer Staff Team Member Held 05/26/2026
    November 24, 2025 7:00 PM Public Hearing Governor Hunt House Community Center
Physical
322 Governor Hunt Road
Vernon, VT 05354
Noticed Hearing Officer Staff Team Member Held 11/24/2025
    November 24, 2025 6:30 PM Project Information Presentation Governor Hunt House Community Center
Physical
322 Governor Hunt Road
Vernon, VT 05354
Noticed Held 11/24/2025 11/24/25 7:00 PM
    November 24, 2025 2:00 PM Site Visit Noticed Hearing Officer Staff Team Member Held 11/24/2025
    October 31, 2025 3:00 PM Scheduling Conference via videoconference Noticed Hearing Officer Staff Team Member Held 10/31/2025
Due Date Name Related to Filed by
09/08/2026
Due Date for Comments on Proposal for Decision
08/21/26 Proposal for Decision
Commission Issued
06/23/2026
Due Date for Reply Briefs
25-2412-PET
06/09/2026
Due Date for Initial Briefs
25-2412-PET
05/22/2026
Petitioner files rebuttal or other supplemental pre-filed testimony
25-2412-PET
05/22/2026
parties submit a proposal containing the information specified in the 5/11/26 Memorandum by 5/22/26
25-2412-PET
05/22/2026
parties must file as an exhibit in ePUC a stipulated joint list of all prefiled testimony and exhibits for which there is no objection by 5/22/26
25-2412-PET
05/22/2026
parties must file any cross-exhibits and any corrected prefiled testimony (with corrections clearly marked) in ePUC that they are planning to move to admit by 5/22/26
25-2412-PET
05/04/2026
Answers to Petitioner’s discovery requests are due
25-2412-PET
04/13/2026
Petitioner to serve discovery requests on other parties
25-2412-PET
03/30/2026
Pre-filed testimony is due from any party other than Petitioner
25-2412-PET
03/10/2026
Petitioner files supplemental testimony on decommissioning
25-2412-PET
03/06/2026
If Matter is Contested: Parties file proposed schedule for remainder of litigation
25-2412-PET
03/02/2026
If Matter is Not Contested by Any Party: Deadline for comments/stipulation(s) and associated testimony/exhibits (if any settlements are reached); Petitioner files proposed findings of fact, order, and certificate of public good
25-2412-PET
02/02/2026
Petitioner responds to second round of Discovery
25-2412-PET
02/02/2026
Petitioner is directed to respond to the 12/31/25 information requests with written testimony by February 2, 2026
25-2412-PET
01/19/2026
Second round of Discovery served on Petitioner (if needed)
25-2412-PET
01/09/2026
Petitioner is directed to respond to the 12/9/25 information requests with written testimony by January 9, 2026
25-2412-PET
12/22/2025
Petitioner responds to first round of Discovery
25-2412-PET
12/02/2025
Response to Motions to Intervene
25-2412-PET
12/01/2025
First Round of Discovery Served on Petitioner
25-2412-PET
11/25/2025
Deadline for Motions to Intervene
25-2412-PET
 
Print this Page