10/08/2025
|
Response to Motion Due Date
|
09/24/25 Motion - Other
|
Green Mountain Power Corporation [PET]
|
|
|
09/12/2025
|
parties submit a proposal containing the information specified in the 9/5/25 Memo by Friday September 12, 2025
|
25-0719-TF
|
|
|
|
09/12/2025
|
parties are also requested to file stipulations or agreements on substantive issues, if any, no later than Friday September 12, 2025
|
25-0719-TF
|
|
|
|
08/15/2025
|
Deadline for GMP and the Department to file any stipulations or agreements and to propose a process for additional proceedings, if necessary.
|
25-0719-TF
|
|
|
|
08/11/2025
|
Department files direct testimony
|
25-0719-TF
|
|
|
|
07/21/2025
|
GMP responds to second round of discovery (narrative responses to be filed in ePUC)
|
25-0719-TF
|
|
|
|
07/16/2025
|
Responses to motions to intervene due
|
25-0719-TF
|
|
|
|
07/14/2025
|
Department serves second round of discovery on GMP
|
25-0719-TF
|
|
|
|
07/11/2025
|
Deadline for motions to intervene
|
25-0719-TF
|
|
|
|
07/07/2025
|
GMP responds to first round of discovery (narrative responses to be filed in ePUC)
|
25-0719-TF
|
|
|
|
06/20/2025
|
Department serves first round of discovery on GMP
|
25-0719-TF
|
|
|
|
06/06/2025
|
Dept of Public Service & GMP must jointly file a proposed procedural schedule for the investigation or separate schedules if unable to stipulate to a joint schedule by 6/6/25
|
25-0719-TF
|
|
|
|
05/15/2025
|
DPS Recommendation Due (30 days)
|
25-0719-TF
|
|
|
|
05/12/2025
|
Due Date for Response to Commission Questions
|
05/6/25 Commission request for information
|
Commission Issued
|