02/28/2031
|
Compliance-Every three years thereafter CPG Holder to file report describing any changes to the decommissioning fund in the previous 3-year period
|
24-3571-PET
|
|
|
|
02/28/2028
|
Compliance-Every three years thereafter CPG Holder to file report describing any changes to the decommissioning fund in the previous 3-year period
|
24-3571-PET
|
|
|
|
10/06/2025
|
Compliance-CPG Holder to file proof of recording notice of CPG in municipal land records
|
24-3571-PET
|
|
|
|
06/20/2025
|
If no stipulation or agreement-Deadline for other parties to file testimony and exhibits
|
24-3571-PET
|
|
|
|
06/20/2025
|
If no stipulation or agreement-Deadline for parties to file proposed schedule for remainder of proceeding
|
24-3571-PET
|
|
|
|
06/13/2025
|
If stipulation or parties reach agreement-Deadline for proposed findings
|
24-3571-PET
|
|
|
|
05/23/2025
|
Deadline for other parties to file comments and any requests for hearing
|
24-3571-PET
|
|
|
|
05/23/2025
|
If stipulation or parties reach agreement-Deadline for parties to file stipulations (or associated testimony and exhibits)
|
24-3571-PET
|
|
|
|
05/02/2025
|
Deadline for Reservoir Solar to respond to round II discovery
|
24-3571-PET
|
|
|
|
04/11/2025
|
Deadline for round II discovery on Reservoir Solar by parties
|
24-3571-PET
|
|
|
|
03/14/2025
|
Deadline for Reservoir Solar responses to round I discovery
|
24-3571-PET
|
|
|
|
02/21/2025
|
Deadline for responses to motions to intervene
|
24-3571-PET
|
|
|
|
02/21/2025
|
Deadline for round I discovery on Reservoir Solar by parties
|
24-3571-PET
|
|
|
|
02/14/2025
|
Deadline for motions to intervene
|
24-3571-PET
|
|
|
|
02/14/2025
|
deadline for requesting public hearing and/or site visit
|
24-3571-PET
|
|