02/13/2026
|
filing by 2/13/25 which states the total costs and number of poles
inspected and treated in the 2025 rate year -filing to be made in compliance subcase
|
24-3432-TF
|
|
|
|
09/12/2025
|
filing by 9/12/25 including confirmation that contract was awarded as a result of VEC’s Pole Inspection & Treatment Request for Proposal, copy of executed contract & date contracted work commenced-filing to be made in compliance subcase
|
24-3432-TF
|
|
|
|
07/11/2025
|
Reply briefs due
|
24-3432-TF
|
|
|
|
06/30/2025
|
Initial briefs due
|
24-3432-TF
|
|
|
|
05/29/2025
|
Department/intervenors to file surrebuttal testimony
|
24-3432-TF
|
|
|
|
05/15/2025
|
VEC to file responses to discovery
|
24-3432-TF
|
|
|
|
05/08/2025
|
Department/intervenors to file discovery on VEC
|
24-3432-TF
|
|
|
|
05/01/2025
|
VEC to file rebuttal testimony
|
24-3432-TF
|
|
|
|
04/24/2025
|
Department/intervenors to file responses to discovery
|
24-3432-TF
|
|
|
|
04/11/2025
|
Discovery to be served on Department/intervenors
|
24-3432-TF
|
|
|
|
04/03/2025
|
Department/intervenors to file direct testimony
|
24-3432-TF
|
|
|
|
03/13/2025
|
VEC to file responses to Department/intervenor discovery
|
24-3432-TF
|
|
|
|
02/27/2025
|
Department/intervenors discovery to be served on VEC
|
24-3432-TF
|
|
|
|
02/26/2025
|
Response to Motion Due Date
|
02/12/25 Motion - Approval of Protective Agreement
|
Vermont Electric Cooperative Inc. [PET]
|
|
|
02/25/2025
|
Deadline for responses to motions to intervene
|
24-3432-TF
|
|
|
|
02/20/2025
|
Deadline for motions to intervene
|
24-3432-TF
|
|
|
|
02/13/2025
|
VEC to file responses to first round of discovery
|
24-3432-TF
|
|
|
|
01/23/2025
|
First round of discovery to be served on VEC
|
24-3432-TF
|
|
|
|
12/16/2024
|
DPS Recommendation Due (30 days)
|
24-3432-TF
|
|