Vermont Public Utility Commission

24-2797-PET Vermont Renewable Gas 2.2 MW facility in Lyndon, VT Open Case Age: 747
Regulatory / Petition: Open Date filed: 08/26/24
Hearing Officer   Date Administratively Complete: 09/3/24
Vermont Renewable Gas LLC [Petitioner]  
Town of Lyndon Electric Department [Utility Company]   Electric
1 Issue(s):§ 248   1 Location(s):Lyndon  

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    August 24, 2026 9:30 AM Evidentiary Hearing via videoconference Noticed Hearing Officer Held 08/24/2026
    April 30, 2026 7:00 PM Public Hearing via videoconference Noticed Hearing Officer Held 04/30/2026
    April 30, 2026 6:30 PM Project Information Presentation via videoconference Noticed Held 04/30/2026
    April 23, 2026 11:00 AM Site Visit Noticed Hearing Officer Held 04/23/2026
    October 29, 2025 9:30 AM Scheduling Conference via videoconference Noticed Hearing Officer Held 10/29/2025
Due Date Name Related to Filed by
08/24/2026
Evidentiary hearing, with briefing schedule determined at hearing
24-2797-PET
08/24/2026
Deadline for parties to file responses to VRG’s objections
08/11/26 Procedural Order Requesting Comments
Commission Issued
08/18/2026
Deadline for surrebuttal testimony by non-petitioners
24-2797-PET
08/18/2026
Due date for parties to make appropriate filings if parties have any issues regarding the following procedures and logistics that need to be addressed before the morning of the hearing
24-2797-PET
08/18/2026
Due date for parties to submit a proposal containing the information specified in 8/10/26 memorandum
24-2797-PET
07/28/2026
Deadline for VRG to respond to discovery
24-2797-PET
07/07/2026
Deadline for discovery on VRG concerning VRG rebuttal testimony
24-2797-PET
06/23/2026
Deadline for VRG to file rebuttal testimony
24-2797-PET
06/16/2026
Deadline for non-petitioners to respond to discovery
24-2797-PET
05/19/2026
Deadline for discovery on non-petitioners
24-2797-PET
05/15/2026
Deadline for testimony by non-petitioner parties
24-2797-PET
04/21/2026
Deadline for supplemental testimony by VRG
24-2797-PET
04/15/2026
Deadline for proposed site visit itineraries
24-2797-PET
04/08/2026
Deadline for discovery on non-petitioners
24-2797-PET
03/30/2026
Response to Motion Due Date
03/16/26 Motion - Other
Simakaski, Mark [P], Dolgin, Steve [P], Ling, John [P], Hastings, Ernest and Madeline [P]
03/20/2026
Deadline for VRG to file rebuttal testimony
24-2797-PET
03/13/2026
Deadline for non-petitioners to respond to discovery
24-2797-PET
02/13/2026
Deadline for discovery on non-petitioners
24-2797-PET
01/30/2026
Deadline for testimony by non-petitioner parties
24-2797-PET
12/23/2025
Deadline for VRG responses to discovery
24-2797-PET
12/03/2025
Deadline for discovery on VRG
24-2797-PET
11/24/2025
Response to Motion Due Date
11/10/25 Motion to Intervene
Simakaski, Mark [P]
11/17/2025
Deadline for responses to motions to intervene
24-2797-PET
11/10/2025
Deadline for motions to intervene and deadline for requesting public hearing and/or site visit
24-2797-PET
11/03/2025
Deadline for VRG to file supplemental testimony
24-2797-PET
10/15/2025
Parties are requested to file proposed schedules for this proceeding by Wednesday, October 15, 2025
24-2797-PET
10/25/2024
Response to Motion Due Date
10/4/24 Motion to Intervene
Conservation Law Foundation [P]
10/25/2024
Response to Motion Due Date
10/9/24 Motion to Intervene
Dolgin, Steve [P]
10/07/2024
Due Date for Comments
24-2797-PET
09/27/2024
Response to Motion Due Date
09/13/24 Motion to Intervene
Town of Lyndon Electric Department [P]
 