12/12/2023
|
Sent email notification regarding new status 'Closed' of SubCase 'Petition' to Thomas Lyle [tlyle@burlingtonelectric.com], Megan Ludwig, Esq. [megan.ludwig@vermont.gov]
|
|
|
12/12/2023
|
Status for SubCase 'Petition' changed from 'Open' to 'Closed'
|
|
|
11/03/2023
|
Sent email notification regarding the issuance of 'Order - Other Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
11/03/2023
|
11/3/23
Order - Other Order Approving Part of the City of Burlington Electric Department's Request to Transfer Funds issued and entered
|
|
|
11/03/2023
|
Sent email notification regarding the issuance of 'Order - Other Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
11/03/2023
|
11/3/23
Order - Other Order Denying Motion to Reconsider issued and entered
|
|
|
09/01/2023
|
Sent email notification regarding filing of 'Response to Motion Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
09/01/2023
|
09/1/23
Response to Motion
filed by Vermont Department of Public Service [P]
in response to Motion - Reconsideration filed by Pike Porter [P]
|
|
|
09/01/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
09/01/2023
|
09/1/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
08/30/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/30/2023
|
08/30/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
08/28/2023
|
Sent email notification regarding filing of 'Comments Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/28/2023
|
08/28/23
Comments
Department of Public Service Response to Commission Procedural Order Requesting Comments
filed by Vermont Department of Public Service [P]
|
|
|
08/23/2023
|
'Motion to Intervene'
filed by Pike Porter [P]
on 08/17/23 changed to 'Motion - Reconsideration'
|
|
|
08/23/2023
|
Sent email notification regarding the issuance of 'Order re Schedule Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/23/2023
|
08/23/23
Order re Schedule Order Granting Extension and Requesting Comments issued and entered
|
|
|
08/18/2023
|
Sent email notification regarding filing of 'Other response Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/18/2023
|
08/18/23
Other response BED Response to Public Comments
filed by City of Burlington Electric Department [PET]
|
|
|
08/17/2023
|
Sent email notification regarding filing of 'Comments Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/17/2023
|
08/17/23
Comments
Department of Public Service Request for Extension of Time
filed by Vermont Department of Public Service [P]
|
|
|
08/16/2023
|
Sent email notification regarding filing of 'Motion to Intervene Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/16/2023
|
08/17/23
Motion to Intervene
of Pike Porter [P], pro se
|
|
|
08/11/2023
|
Sent email notification regarding filing of 'Other response Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov]
|
|
|
08/11/2023
|
08/11/23
Other response BED Response to DPS Questions
filed by City of Burlington Electric Department [PET]
|
|
|
08/01/2023
|
Sent email notification regarding the issuance of 'Hearing Officer request for information Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov]
|
|
|
08/01/2023
|
08/1/23
Hearing Officer request for information of
issued
|
|
|
08/01/2023
|
Sent email notification regarding the issuance of 'Order re Motion to Intervene Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
08/01/2023
|
08/1/23
Order re Motion to Intervene Order Denying Motion to Intervene and Requesting Response to Public Comments issued and entered
|
|
|
07/18/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/18/2023
|
07/18/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
07/13/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/13/2023
|
07/3/23
Public Comment
filed by Steven Goodkind [PUBCOM]
|
|
|
07/13/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/13/2023
|
07/3/23
Public Comment
filed by Patrick Flood [PUBCOM]
|
|
|
07/13/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/13/2023
|
07/3/23
Public Comment
filed by Catherine Bock [PUBCOM]
|
|
|
07/12/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/12/2023
|
07/3/23
Public Comment
filed by Nick Persampier [PUBCOM]
|
|
|
07/05/2023
|
Sent email notification regarding filing of 'Reply to Response Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/05/2023
|
07/5/23
Reply to Response
filed by Pike Porter [P]
|
|
|
07/05/2023
|
Sent email notification regarding filing of 'Motion to Intervene Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/05/2023
|
Sent email notification regarding filing of 'Motion to Intervene Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/05/2023
|
07/5/23
Motion to Intervene
on behalf of Pike Porter [P]
filed by
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Peter K. Duval [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Peter K. Duval [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Mari Miceli [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Levi M. Robert [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Response to Motion Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Response to Motion
filed by Vermont Department of Public Service [P]
in response to Motion to Intervene filed by Pike Porter [P]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Public Comment
filed by Daniel Batten [PUBCOM]
|
|
|
07/03/2023
|
Sent email notification regarding filing of 'Comments Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/03/2023
|
07/3/23
Comments
Department of Public Service Response to PUC June 9th Procedural Order
filed by Vermont Department of Public Service [P]
|
|
|
07/02/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/02/2023
|
07/3/23
Public Comment
filed by Chris Gish [PUBCOM]
|
|
|
07/02/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/02/2023
|
07/3/23
Public Comment
filed by Suzanne McCoy [PUBCOM]
|
|
|
07/01/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/01/2023
|
07/3/23
Public Comment
filed by Nick Persampieri [PUBCOM]
|
|
|
07/01/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/01/2023
|
07/3/23
Public Comment
filed by Jud J. Lawrie [PUBCOM]
|
|
|
07/01/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
07/01/2023
|
07/3/23
Public Comment
filed by Alex Messinger [PUBCOM]
|
|
|
06/30/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/30/2023
|
07/3/23
Public Comment
filed by Laura Zakaras [PUBCOM]
|
|
|
06/29/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/29/2023
|
06/29/23
Public Comment
filed by Nora Thomas [PUBCOM]
|
|
|
06/29/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/29/2023
|
06/29/23
Public Comment
filed by Ashley Adams [PUBCOM]
|
|
|
06/28/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/28/2023
|
06/27/23
Public Comment
filed by Brian Forrest [PUBCOM]
|
|
|
06/28/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/28/2023
|
06/28/23
Public Comment
filed by Andrew Rianhard [PUBCOM]
|
|
|
06/28/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/28/2023
|
06/28/23
Public Comment
filed by Brynne Martin [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/28/23
Public Comment
filed by Webster David [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/28/23
Public Comment
filed by Zack Porter [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/28/23
Public Comment
filed by Connor Wertz [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/28/23
Public Comment
filed by Connor Wertz [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/28/23
Public Comment
filed by Cheryl J. Lipton [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/27/23
Public Comment
filed by Phillip D. Merrick [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/27/23
Public Comment
filed by Dan Castrigano [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/27/23
Public Comment
filed by Laura Simon [PUBCOM]
|
|
|
06/27/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/27/2023
|
06/27/23
Public Comment
filed by Catherine Bock [PUBCOM]
|
|
|
06/21/2023
|
Sent email notification regarding the issuance of 'Order re Schedule Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/21/2023
|
06/21/23
Order re Schedule Procedural Order Requesting Comment issued and entered
|
|
|
06/21/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/21/2023
|
06/21/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
06/21/2023
|
Sent email notification regarding filing of 'Public Comment Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/21/2023
|
06/21/23
Public Comment
filed by Pike Porter [PUBCOM]
|
|
|
06/19/2023
|
Sent email notification regarding filing of 'Motion to Intervene Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov], Pike Porter[pikeporter@gmail.com]
|
|
|
06/19/2023
|
06/19/23
Motion to Intervene
of Pike Porter [P], pro se
|
|
|
06/09/2023
|
Sent email notification regarding the issuance of 'Procedural Order Requesting Comments Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Megan Ludwig, Esq.[megan.ludwig@vermont.gov]
|
|
|
06/09/2023
|
06/9/23
Procedural Order Requesting Comments Procedural Order issued and entered
|
|
|
06/07/2023
|
Sent email notification regarding filing of 'Notice of Appearance Document' to Thomas Lyle[tlyle@burlingtonelectric.com], Director of Public Advocacy[DPS-PA@vermont.gov], Megan Ludwig, Esq.[megan.ludwig@vermont.gov]
|
|
|
06/07/2023
|
06/7/23
Notice of Appearance
of Megan Ludwig, Esq. [REP] on behalf of Vermont Department of Public Service [P]
|
|
|
06/02/2023
|
Sent email notification regarding new status 'Open' of SubCase 'Petition' to Thomas Lyle [tlyle@burlingtonelectric.com], Director of Public Advocacy [DPS-PA@vermont.gov]
|
|
|
06/02/2023
|
Status for SubCase 'Petition' changed from 'eFiled' to 'Open'
|
|
|
06/02/2023
|
Sent email notification regarding the creation of SubCase 'Petition' to Thomas Lyle [tlyle@burlingtonelectric.com], Director of Public Advocacy [DPS-PA@vermont.gov]
|
|
|
06/02/2023
|
SubCase 'Petition' was inserted
|
|
|
06/02/2023
|
06/2/23
Petition
filed by City of Burlington Electric Department [PET]
|
|
|
06/02/2023
|
Regulatory case 23-1870-PET, , (Energy Efficiency Utility) filed
|