Vermont Public Utility Commission

19-3272-PET DPS Petition re EEU DRP for 2021-2023 Closed Case Age: 14
Regulatory / Petition: Closed
                                                     Required Compliance Filings: Closed
Date filed: 08/15/19
Hearing Officer Commissioner  
Vermont Department of Public Service [Petitioner]  
Energy Efficiency Utility
1 Issue(s):Other    

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    May 7, 2021 9:30 AM Evidentiary Hearing via videoconference Noticed Staff Team Member Staff Team Member Staff Team Member Staff Team Member Cancelled 05/04/2021
    October 20, 2020 9:30 AM Status Conference via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 10/20/2020
    July 23, 2020 9:30 AM Evidentiary Hearing via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 07/23/2020
    July 16, 2020 1:30 PM Status Conference via videoconference Noticed Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 07/16/2020
    January 31, 2020 9:30 AM Workshop Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 01/31/2020
    January 13, 2020 1:30 PM Scheduling Conference Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 01/13/2020 1/13/20 4:30 PM
    January 13, 2020 1:30 PM Workshop Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Staff Team Member Staff Team Member Held 01/13/2020 1/13/20 4:30 PM
    September 12, 2019 9:30 AM Workshop Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Commissioner Staff Team Member Held 09/12/2019
  Required Compliance Filings
Due Date Name Related to Filed by
10/17/2023
deadline for comments on Efficiency Vermont’s 9/29/23 request in 22-2954-PET is Tuesday, October 17, 2023
19-3272-PET
03/31/2023
Due Date for Party Comments
03/15/23 Procedural Order Requesting Comments
Commission Issued
06/17/2022
Due date for reply comments and any requests for additional process
19-3272-PET
06/03/2022
Due Date for Party Comments
05/18/22 Procedural Order Requesting Comments
Commission Issued
01/17/2022
Any comments on BED’s 12/17/21 filing are due no later than January 17, 2022
19-3272-PET
12/06/2021
Due date for any comments addressing Efficiency Vermont’s request
19-3272-PET
10/12/2021
Any comments BED's filing and any requests for additional process due
19-3272-PET
09/27/2021
BED shall file for Commission approval proposed administrative cost budgets based on the budgets approved in this Order and the previously approved definition of “administrative costs.”
19-3272-PET
09/22/2021
VGS to file & DPS invited to file, a bibliography of all literature and other sources reviewed in the investigation of performance incentive mechanisms, including those in other jurisdictions
19-3272-PET
08/23/2021
Due date for comments to information request responses should be filed by 12 p.m. on August 23,2021
19-3272-PET
08/17/2021
Due Date for information request
08/6/21 Procedural Order Requesting Comments
Commission Issued
08/04/2021
Due Date for Comments on Proposal for Decision
07/20/21 Proposal for Decision
Commission Issued
08/03/2021
Response to Motion Due Date
07/20/21 Motion - Other
Vermont Gas Systems, Inc. [P]
07/12/2021
VGS's performance incentive mechanism proposal shall be filed as a new petition case by 7/12/21
19-3272-PET
07/02/2021
Any other requests for hearing or reply briefs should be filed by July 2, 2021.
19-3272-PET
06/23/2021
BED to file proposed order-state whether it seeks to reschedule the evidentiary hearing and to identify which documents that have not yet been admitted that BED would like admitted into evidence
19-3272-PET
06/07/2021
Due Date for Response to Commission Questions
05/24/21 Commission request for information
Commission Issued
05/28/2021
If hearing requested, tentative date for Hearing Officer decision (no earlier then deadline) re: Efficiency Vermont
19-3272-PET
05/17/2021
Parties to file status update re revised BED DRP
19-3272-PET
05/14/2021
If no hearing requested, tentative date for Commission decision (no earlier then deadline) re: Efficiency Vermont
19-3272-PET
05/14/2021
If hearing requested,deadline for parties to file briefs re: Efficiency Vermont
19-3272-PET
05/10/2021
Deadline for Department/other stakeholder responses to discovery requests re revised BED DRP
19-3272-PET
05/07/2021
If no hearing requested, deadline for responses to Commission information requests re: Efficiency Vermont
19-3272-PET
05/07/2021
Due Date for Response to Commission Questions
04/23/21 Commission request for information
Commission Issued
04/30/2021
Deadline for parties to file request for hearing re: Efficiency Vermont
19-3272-PET
04/30/2021
If no hearing requested, deadline for parties to file response to Efficiency Vermont submission re: Efficiency Vermont
19-3272-PET
04/30/2021
If no hearing requested, deadline for parties to file waiver of opportunity for hearing and consent to admission of prefiled testimony and exhibits, and waiver of opportunity to comment on Hearing Officer proposal for decision re: Efficiency Vermont
19-3272-PET
04/30/2021
If hearing requested, deadline for parties to file response to Efficiency Vermont submission re: Efficiency Vermont
19-3272-PET
04/27/2021
Deadline for discovery requests from BED re revised BED DRP
19-3272-PET
04/23/2021
Response to Motion Due Date
04/9/21 Motion - Change Schedule
Efficiency Vermont - Vermont Energy Investment Corporation [P]
04/23/2021
Deadline for Commission to serve information requests (if any) re: Efficiency Vermont
19-3272-PET
04/20/2021
Deadline for Department and other stakeholder testimony re revised BED DRP
19-3272-PET
04/16/2021
Deadline for Efficiency Vermont to file proposal for decision re: Efficiency Vermont
19-3272-PET
04/16/2021
Deadline for Efficiency Vermont to file waiver of opportunity for hearing and consent to admission of prefiled testimony and exhibits; and waiver of opportunity to comment on Hearing Officer proposal for decision re: Efficiency Vermont
19-3272-PET
04/12/2021
VGS shall file 6-month status report regarding its investigations on the implementation of a performance incentive mechanism that rewards performance relative to efficiency goals rather than spending
19-3272-PET
04/12/2021
Deadline for discovery on Department's and other parties' supplemental rebuttal testimony and exhibits re Efficiency Vermont’s amended Demand Resource Plan
19-3272-PET
04/02/2021
Deadline for BED responses to discovery requests re revised BED DRP
19-3272-PET
04/02/2021
Response to Motion Due Date
03/19/21 Motion - Other
City of Burlington Electric Department [P]
03/31/2021
Deadline for Department and other parties to file supplemental rebuttal testimony and exhibits re: Efficiency Vermont’s Amended Demand Resource Plan
19-3272-PET
03/26/2021
Deadline for discovery requests on BED re revised BED DRP
19-3272-PET
03/24/2021
BED files supplemental testimony re revised BED DRP
19-3272-PET
03/17/2021
Deadline for discovery responses
19-3272-PET
03/10/2021
Deadline for discovery on Efficiency Vermont's supplemental testimony and exhibits
19-3272-PET
03/05/2021
deadline for reply comments and recommendations for further process is March 5, 2021
19-3272-PET
02/26/2021
Response to Motion Due Date
02/12/21 Motion - Other
Efficiency Vermont - Vermont Energy Investment Corporation [P]
02/19/2021
deadline for comments on Efficiency Vermont proposal is February 19, 2021
19-3272-PET
02/05/2021
deadline for Efficiency Vermont to file a proposal is February 5, 2021
19-3272-PET
01/25/2021
BED files status update
19-3272-PET
01/20/2021
VGS shall file 3-month status report regarding its investigations on the implementation of a performance incentive mechanism that rewards performance relative to efficiency goals rather than spending
19-3272-PET
01/14/2021
Deadline for Department testimony
19-3272-PET
12/18/2020
Deadline for responses to information requests
19-3272-PET
12/10/2020
Deadline for rolling information requests
19-3272-PET
11/23/2020
VGS to file proposed administrative cost budgets based on the budgets approved in this Order and the previously approved definition of “administrative costs.”
19-3272-PET
11/23/2020
VGS shall file weighting factors for the Addison County-specific QPIs or shall explain why it is appropriate for those QPIs to remain unweighted.
19-3272-PET
11/23/2020
VGS shall file new targets for MPR #14, explain why the 30% target remains appropriate, or propose a new Addison County-specific MPR within 30 days of this Order.
19-3272-PET
11/23/2020
Eff. VT to file compliance filing within 30 days re: tables containing information requested in Order paragraph #8 of 10/22/20 Order
19-3272-PET
11/23/2020
Eff. VT to file compliance filing within 30 days re:proposed administrative cost budgets based on the budgets approved in this Order and the previously approved definition of “administrative costs.”
19-3272-PET
11/23/2020
Eff. VT to file compliance filing within 30 days re: any updates to the approved 20-year forecast of electric savings based on the quantifiable performance indicator targets approved in this Order as requested in Order paragraph #11 of 10/22/20 Order
19-3272-PET
11/20/2020
BED files comprehensive amended DRP proposal, Act 151 program description
19-3272-PET
10/16/2020
Efficiency Vermont to file response to 10/12/20 Order request by 10/16/20
19-3272-PET
10/14/2020
Due Date for Reply Comments pursuant to the 10/9/20 Order Requesting Parties to Confirm the Record
10/9/20 Procedural Order Requesting Reply Comments
Commission Issued
10/09/2020
BED is requested to file corrected DRP containing updated charts in the final proposed DRP to match the testimony it has submitted. BED is encouraged to also revise the text of the final proposed DRP as may be needed to align with charts
19-3272-PET
09/21/2020
Any objections to the admissibility of the responses to Commission info requests into the record, and any requests for additional process–including a continuation of the evidentiary hearing due
19-3272-PET
09/14/2020
Due Date for Response to Commission Questions
09/3/20 Commission request for information
Commission Issued
09/11/2020
Reply briefs addressing the DRPs for Efficiency Vermont and the City of Burlington Electric Department and the evaluation plan for the Department due
19-3272-PET
08/21/2020
With Surrebuttal: Deadline for briefs
19-3272-PET
08/12/2020
Response to Motion Due Date
07/29/20 Motion - Withdraw as Representative
Conservation Law Foundation [P]
07/16/2020
Responses to Hearing Officer Info Requests Due
19-3272-PET
07/10/2020
With Surrebuttal: Deadline for discovery responses regarding surrebuttal testimony
19-3272-PET
06/26/2020
With Surrebuttal: Deadline for discovery on surrebuttal testimony
19-3272-PET
06/19/2020
With Surrebuttal: Deadline for surrebuttal testimony (discovery begins with 14-day response)
19-3272-PET
05/27/2020
Deadline for requests to file surrebuttal testimony
19-3272-PET
05/22/2020
Deadline for discovery responses from Efficiency Vermont and BED regarding rebuttal testimony
19-3272-PET
05/22/2020
Deadline for discovery responses from Vermont Gas regarding rebuttal testimony
19-3272-PET
05/08/2020
Deadline for discovery on Vermont Gas rebuttal testimony
19-3272-PET
05/01/2020
Deadline for discovery on Efficiency Vermont and BED rebuttal testimony
19-3272-PET
05/01/2020
Deadline for rebuttal testimony and evidence from Vermont Gas (discovery begins with 14-day response)
19-3272-PET
04/17/2020
Deadline for rebuttal testimony and evidence from Efficiency Vermont and BED
19-3272-PET
04/17/2020
Deadline for discovery responses from the Department and other parties addressing their proposals for Vermont Gas
19-3272-PET
04/03/2020
Deadline for discovery responses from the Department and other parties addressing their proposals for Efficiency Vermont and BED
19-3272-PET
04/03/2020
Deadline for discovery on the Department’s and other parties’ proposals for Vermont Gas
19-3272-PET
03/27/2020
Deadline for testimony and proposals from the Department and other parties addressing the Vermont Gas proposal (discovery begins with 14-day response)
19-3272-PET
03/13/2020
Deadline for discovery on the Department’s and other parties’ proposals for Efficiency Vermont and BED
19-3272-PET
03/04/2020
Response to Motion Due Date
02/19/20 Motion - Change Schedule
Vermont Public Power Supply Authority [P]
02/28/2020
Deadline for VPPSA to file direct testimony
19-3272-PET
02/25/2020
Deadline for Vermont Gas discovery responses
19-3272-PET
02/21/2020
Deadline for testimony and proposals from the Department and other parties addressing the Efficiency Vermont and BED proposals
19-3272-PET
02/21/2020
Deadline for the Department to file proposed measurement and evaluation plan (discovery begins with 21-day response)
19-3272-PET
02/11/2020
Deadline for discovery on the Vermont Gas proposal
19-3272-PET
02/07/2020
Deadline for Efficiency Vermont and BED discovery responses
19-3272-PET
01/24/2020
Deadline for discovery on the Efficiency Vermont and the City of Burlington Electric Department (“BED”) proposals
19-3272-PET
01/13/2020
Schedule Proposals & Workshop Slides Due
19-3272-PET
12/27/2019
Responses to VGS Motion to Extend Schedule Due
19-3272-PET
12/20/2019
Due date for the EEUs to file Demand Resources Plan (“DRP”) proposals with pre-filed testimony in ePUC.
19-3272-PET
12/06/2019
Due date for reply comments to be filed in PUC addressing the Department’s potential study with rate and bill impacts.
19-3272-PET
11/22/2019
Due date for comments to be filed in ePUC addressing the Department’s potential study with rate and bill impacts.
19-3272-PET
 
Print this Page