Vermont Public Utility Commission

22-2954-PET Department request to open EEU Demand Resources Plan proceeding Open Case Age: 867
Regulatory / Petition: Open
                                                     Required Compliance Filings: Pending Required Compliance Filings
Date filed: 07/27/22
Commissioner  
Vermont Department of Public Service [Petitioner]  
Energy Efficiency Utility
1 Issue(s):Other    

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    February 8, 2024 9:30 AM Status Conference via videoconference Noticed Staff Team Member Staff Team Member Held 02/08/2024
    June 27, 2023 9:30 AM Evidentiary Hearing via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Held 06/27/2023
    April 21, 2023 9:30 AM Scheduling Conference via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Held 04/21/2023
    February 2, 2023 9:30 AM Workshop via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Lead Staff Team Member Held 02/02/2023
    September 27, 2022 1:30 PM Scheduling Conference via videoconference Noticed Commissioner Commissioner Commissioner Staff Team Member Staff Team Member Held 09/27/2022
  Required Compliance Filings
Due Date Name Related to Filed by
10/16/2024
Deadline for each EEU to file a summary of its completed analysis or status update on information technology costs
22-2954-PET
09/16/2024
Due date for BED to file tables of its approved 2024-2026 QPIs and minimum performance requirements
22-2954-PET
07/10/2024
Due Date for Party Comments
06/18/24 Procedural Order Requesting Comments
Commission Issued
04/19/2024
deadline for responses to the March 11 and March 29 filings is April 19, 2024
22-2954-PET
03/29/2024
deadline for the Department to make supplemental filings examining the tradeoffs of its Act 44 budget proposals is March 29, 2024
22-2954-PET
03/29/2024
March 29, 2024, serves as the deadline for Parties to file stipulated or separate proposals for Act 44 programs covering the years 2025 or 2026
22-2954-PET
03/11/2024
By 3/11/24 BED must make additional filings examining the tradeoffs of its Act 44 proposal for the 2025 and 2026 performance years
22-2954-PET
03/11/2024
By 3/11/24 Efficiency VT must make additional filings examining the tradeoffs of its Act 44 proposal for the 2025 and 2026 performance years
22-2954-PET
01/15/2024
Comments on Efficiency Vermont's revisions to resource-acquisition modeling for the 2024-2026 performance period due-filing to be made in compliance subcase
22-2954-PET
01/15/2024
comments on revisions to tables re: electric quantifiable performance indicators, etc filing due--file in compliance subcase
22-2954-PET
01/10/2024
Tentative date for proposal for decision
22-2954-PET
01/05/2024
Due Date for Reply Comments
12/19/23 Procedural Order Requesting Reply Comments
Commission Issued
12/28/2023
BED to respond to the Department’s comments and Efficiency Vermont to respond to the Department’s and VPPSA’s comments by 12/28/23
22-2954-PET
12/22/2023
deadline for responses to comments
22-2954-PET
12/21/2023
Deadline for responses to Commission information requests
22-2954-PET
12/15/2023
Deadline for comments on BED’s and Efficiency Vermont’s proposals for amended DRPs
22-2954-PET
12/15/2023
Deadline for Commission information requests
22-2954-PET
12/14/2023
Efficiency Vermont must file for Commission approval budget tables to reflect the determinations made in the 11/13/23 Order-filings to be made in compliance subcase
22-2954-PET
12/14/2023
Efficiency Vermont must file for Commission approval any revisions to resource-acquisition modeling for the 2024-2026 performance period to reflect the determinations made in the 11/13/23 Order-filing made in the compliance subcase
22-2954-PET
12/14/2023
Efficiency Vermont file for approval any revisions to tables containing electric quantifiable performance indicators & minimum performance requirements for '24-'26 period to reflect the determinations made in 11/13/23 Order-file in compliance subcase
22-2954-PET
12/01/2023
the deadline for the EEUs to file their triennial plans is December 1, 2023
22-2954-PET
12/01/2023
Response to Motion Due Date
11/17/23 Motion - Other
Efficiency Vermont - Vermont Energy Investment Corporation [P]
11/10/2023
Any comments on BED, VGS, and Efficiency Vermont's compliance filings should be filed by November 10, 2023.
22-2954-PET
11/03/2023
Response to Motion Due Date
10/20/23 Motion - Other
Efficiency Vermont - Vermont Energy Investment Corporation [P]
11/03/2023
Response to Motion Due Date
10/20/23 Motion - Change Schedule
Efficiency Vermont - Vermont Energy Investment Corporation [P]
11/01/2023
Department file 20-year budgets representing estimates of its future evaluation costs by 11/1/23
22-2954-PET
10/17/2023
deadline for comments on Efficiency Vermont’s 9/29/23 request is Tuesday, October 17, 2023
22-2954-PET
10/13/2023
Response to Motion Due Date
09/29/23 Motion - Other
Efficiency Vermont - Vermont Energy Investment Corporation [P]
09/05/2023
Target date for Commission orders
22-2954-PET
08/08/2023
Deadline for parties’ reply briefs
22-2954-PET
07/25/2023
Deadline for parties’ initial briefs
22-2954-PET
06/27/2023
parties should file any cross-exhibits in ePUC by 9AM 6/27/23
22-2954-PET
06/26/2023
parties are requested to file an updated stipulated joint list of all the prefiled testimony and exhibits for which there is no objection into the evidentiary record by Monday, June 26, 2023
22-2954-PET
06/23/2023
Deadline for parties’ responses to Commission information requests
22-2954-PET
06/23/2023
Due Date for Response to Commission Questions
06/16/23 Commission request for information
Commission Issued
06/20/2023
Deadline for parties to file list of evidence to be admitted into the record, proposed order of witnesses at hearing, and estimates of cross-examination time for each witness
22-2954-PET
06/19/2023
Due date for responses to requests related to presenting surrbuttal testimony, whether live or prefiled, if the request is not unanimously supported.
22-2954-PET
06/16/2023
Commission information requests to parties
22-2954-PET
06/16/2023
Due date for BED, VGS, or Efficiency Vermont to file request if they wish to present surrebuttal testimony, whether live or prefiled.
22-2954-PET
06/02/2023
Deadline for the Department and VPPSA to file surrebuttal testimony
22-2954-PET
05/31/2023
Deadline for Efficiency Vermont, BED, and VGS to file a status report after the conclusion of the legislative session
22-2954-PET
05/11/2023
Deadline for Efficiency Vermont and VGS to file rebuttal testimony
22-2954-PET
05/04/2023
Deadline for BED to file rebuttal testimony
22-2954-PET
04/28/2023
Due Date for Response to Commission Questions
04/12/23 Commission request for information
Commission Issued
04/27/2023
Due Date for Response to Commission Questions
04/12/23 Commission request for information
Commission Issued
04/20/2023
Due Date for Response to Commission Questions
03/30/23 Commission request for information
Commission Issued
04/14/2023
parties to file proposed schedules seven days before scheduling conference
22-2954-PET
04/10/2023
Due Date for Response to Commission Questions
03/28/23 Commission request for information
Commission Issued
03/23/2023
Discovery requests on parties’ Efficiency Vermont reply testimony, with 14-day response
22-2954-PET
03/23/2023
Deadline for reply testimony and exhibits in response to BED proposal
22-2954-PET
03/16/2023
Deadline for reply testimony and exhibits in response to VGS proposal
22-2954-PET
02/27/2023
Due Date for Party Comments
02/15/23 Procedural Order Requesting Comments
Commission Issued
02/22/2023
Due Date for Response to Commission Questions
02/7/23 Commission request for information
Commission Issued
02/16/2023
Last day for discovery requests on VGS and BED proposals, with 14-day response
22-2954-PET
02/01/2023
Response to Motion Due Date
01/18/23 Motion - Other
Efficiency Vermont - Vermont Energy Investment Corporation [P]
01/09/2023
Deadline for responses to motions to intervene
22-2954-PET
12/30/2022
Deadline for motions to intervene
22-2954-PET
12/21/2022
Discovery requests on EEU proposals begins, with 14-day response
22-2954-PET
12/20/2022
Deadline for EEUs to file DRP update proposals accompanied by pre-filed testimony and exhibits
22-2954-PET
09/09/2022
If a workshop is not requested by a stakeholder or the Commission, the deadline for the Department to file written responses shall be September 9, 2022.
22-2954-PET
09/09/2022
Due Date for Response to Commission Questions
08/29/22 Commission request for information
Commission Issued
08/26/2022
August 26, 2022, is the deadline for stakeholders to file written comments, questions, and requests for a workshop regarding the draft potential study results
22-2954-PET
Print this Page