19-0302-INV Investigation to establish Energy Savings Account partnership pilot program Open Case Age: 2282
Regulatory / Investigation: Open Date filed: 01/30/19
 
Energy Efficiency Utility
   

Schedule-Portal

Date/Times Description Location Event
Status
Commission
Personnel
Result Result
Date
Event End
Date/Time
  Investigation
    August 12, 2019 9:30 AM Workshop Susan M. Hudson Hearing Room Noticed Lead Staff Team Member Staff Team Member Held 08/12/2019
    March 19, 2019 9:30 AM Workshop Susan M. Hudson Hearing Room Noticed Lead Staff Team Member Staff Team Member Held 03/19/2019
Due Date Name Related to Filed by
12/01/2023
ESA pilot program participants should file requests for extension by no later than Friday, December 1, 2023
19-0302-INV
03/24/2022
Response to Motion Due Date
03/10/22 Motion - Other
Killington Pico Ski Resort Partners LLC [PART]
11/25/2019
Due Date for Comments on Proposal for Decision
11/14/19 Proposal for Decision
Commission Issued
10/28/2019
Tentative date for Commission Order regarding track two (week of October 28th)
19-0302-INV
09/30/2019
tentative date for hearing officer's proposal for decision regarding track two (week of September 30, 2019)
19-0302-INV
09/10/2019
Deadline for comments on Department's track two recommendations
19-0302-INV
07/12/2019
Due Date for Party Comments
07/2/19 Procedural Order Requesting Comments
Commission Issued
07/01/2019
Deadline for recommendations by Efficiency Vermont, the Department, and ACCD for ESA pilot program participants
19-0302-INV
05/06/2019
Request for proposals issued by Efficiency Vermont, the Department, and ACCD are due the week of May 6, 2019
19-0302-INV
05/03/2019
Due Date for Comments on Proposal for Decision
04/22/19 Proposal for Decision
Commission Issued
04/22/2019
Tentative date for Commission Order regarding the criteria for customer selection to the ESA pilot program will be the week of April 22, 2019
19-0302-INV
04/08/2019
Tentative date for Hearing Officer's proposal for decision regarding the criteria for customer selection to the ESA pilot program will be the week of April 8,2019
19-0302-INV
03/26/2019
Deadline for comments on recommendations
19-0302-INV
03/15/2019
Deadline for Efficiency Vermont, Department, and ACCD to file recommendations regarding the criteria for customer selection
19-0302-INV